Progress
What is done, what is next and what blocks it. The date of this page is 2026-10-20.
- DoneMilestone 1: R core
- DoneMilestone 2: Browser engine and projects
- DoneMilestone 3A: Translation service
- DoneChanges from the first review
- DoneMilestone 3B: Interface
- DoneMilestone 3C: Exports, import and report
- DoneAlpha release
- DoneAlpha minor fixes
- DoneReport print redesign
- NowAlan's review and the fixes
- PlannedMilestone 4: Evaluation and documentation
- PlannedPhase 2: Analysis
- PlannedIntroduction video
- PlannedPhase 3: Blocking, split-plot and foldover
- PlannedPhase 4: Other design families
- NowProject pages
Next: Alan's review and the fixes
- Answers to the four questions asked again on the review page (live since 2026-10-20) and to the refused FrF2 defaults (after the revision of the FrF2 findings)
- Check in the Upstash console that the counter keys have a time limit
Then: Milestone 4: Evaluation and documentation
- Review of the gold labels (Section 12.1).
- The rule for the production default, with X, Y and Z (Section 12.4).
- A save of the R library that fails after IndexedDB opens (for example a full quota) leaves the engine start without an answer from WebR 0.6.0. The user sees "loading has stopped" and Retry.
- Jev's outcome criteria misjudge some design requests, for example requests with level ranges (Section 3.3). Review the wording before Jev's outcome counts again.
- Measure the video title cards again with the accent rule (Section 10.3).
- The field of application. Alan R. Vazquez proposes to tailor EXPERTA to one field (for example biotechnology, the food industry or manufacturing), because the readers of JQT and Quality Engineering already know FrF2 (his comment of 2026-10-19, decision F13). He will search for papers on applications to choose the field. His answers stay out of the public repository (Section 14.4).
Now
GitHub data was read on 2026-10-20 at 16:49 UTC.
Production: success at 411dbfb (head of main in fmegahed/experta).
Branches
No branch other than main is open.
Open pull requests
No pull request is open.
Open issues
- #70 [alpha-review] guarantee.no-claim: Change
- #69 [alpha-review] glossary.all_2fis_clear: Agree
- #68 [alpha-review] glossary.guarantee: Agree
- #67 [alpha-review] guarantee.region.128.25-64: Agree
- #65 [alpha-review] other: Comment
- #64 [alpha-review] guarantee.refused-defaults: Not sure
- #63 [alpha-review] guarantee.no-claim: Not sure
- #61 [alpha-review] guarantee.region.128.25-64: Not sure
- #53 [alpha-review] guarantee.region.128.25-64: Not sure
- #46 [alpha-review] glossary.all_2fis_clear: Not sure
- #45 [alpha-review] glossary.all_2fis_clear: Not sure
Completed work by plan
| Plan | Tasks | Final review | Merged | Deployed |
|---|---|---|---|---|
| Milestone 1: R core | One fix wave; re-review: all findings addressed | |||
| Milestone 2: Browser engine and projects | Ready with fixes; one fix wave | |||
| Milestone 3A: Translation service | Clean after one fix wave | |||
| Changes from the first review | Ready to merge; 7 minor findings deferred | |||
| Milestone 3B: Interface | 1 Important finding; one fix wave, re-review clean | |||
| Milestone 3C: Exports, import and report | 3 Important findings; one fix wave, re-review clean | |||
| Alpha release | One fix wave, re-review clean | |||
| Alpha minor fixes | One fix wave (11 items), re-review clean | |||
| Report print redesign | One fix wave (10 items), re-review clean | |||
| Alan's review and the fixes | One fix wave; re-review: all findings addressed | |||
| Project pages | Final review: ready with fixes; one fix wave | Not deployed |
Timeline
Table of the bars
| Plan | State | First commit | End |
|---|---|---|---|
| Milestone 1: R core | done | 2026-10-15 | 2026-10-15 |
| Milestone 2: Browser engine and projects | done | 2026-10-15 | 2026-10-15 |
| Milestone 3A: Translation service | done | 2026-10-15 | 2026-10-16 |
| Changes from the first review | done | 2026-10-16 | 2026-10-16 |
| Milestone 3B: Interface | done | 2026-10-16 | 2026-10-17 |
| Milestone 3C: Exports, import and report | done | 2026-10-17 | 2026-10-17 |
| Alpha release | done | 2026-10-17 | 2026-10-18 |
| Alpha minor fixes | done | 2026-10-18 | 2026-10-19 |
| Report print redesign | done | 2026-10-18 | 2026-10-19 |
| Alan's review and the fixes | now | 2026-10-19 | 2026-10-20 |
| Phase 4: Other design families | planned | 2026-10-19 | Not started |
| Project pages | now | 2026-10-19 | 2026-10-20 |
Before the public release
- Review of the guarantee table (Section 7.7). Done on 2026-10-19 for 12 of the 13 regions, the class sentences and the additions (center points, replications, resolution only). Asked again (Section 14.4): the claim for 128 runs with 25 to 39 factors, and the claims for the other catalogue entries. The refused defaults
26-17.1and27-18.1stay refused until Alan R. Vazquez revises the FrF2 findings. - Review of the glossary (Section 9.5). Done on 2026-10-19 for 33 of the 35 entries drafted in Milestone 3B. The entries
all_2fis_clearandguaranteehave new texts, show "Draft, not yet reviewed" and are asked again (Section 14.4). - A check of the name EXPERTA for conflicts with other software and organizations.
- Self-hosting: a Dockerfile and the ChatISA start script. Self-hosted runs keep the counters in memory; Vercel uses Redis or refuses the request.
scripts/ste-check.mjs, named in Section 14.1, does not exist in the repository.- Measure the main-thread parse of the largest report again under the Content Security Policy. The 40 ms of Milestone 3C was measured with the Zod JIT, which the policy now blocks.
Other open items
The open items of Section 17.1 of the specification that are not above.
Needed by: Phase 2
- Phase 2 upload reads
.xlsxfiles that Excel saves (shared strings, styles); the 3C writer uses inline strings only.
Needed by: Video release with version 1.0
- Review of the Spanish narration.
Needed by: When the authors decide
- Send the FrF2 findings to the FrF2 maintainer (draft in
replication_materials/findings/)
Needed by: Before a Phase 4 plan
- The routing rule of Phase 4: a reviewed decision table (recommended, Section 1.9) or the LLM's own judgment.
- The decision table of Phase 4 and the gold families.