EXPERTA project pages

Progress

What is done, what is next and what blocks it. The date of this page is 2026-10-20.

  1. DoneMilestone 1: R core
  2. DoneMilestone 2: Browser engine and projects
  3. DoneMilestone 3A: Translation service
  4. DoneChanges from the first review
  5. DoneMilestone 3B: Interface
  6. DoneMilestone 3C: Exports, import and report
  7. DoneAlpha release
  8. DoneAlpha minor fixes
  9. DoneReport print redesign
  10. NowAlan's review and the fixes
  11. PlannedMilestone 4: Evaluation and documentation
  12. PlannedPhase 2: Analysis
  13. PlannedIntroduction video
  14. PlannedPhase 3: Blocking, split-plot and foldover
  15. PlannedPhase 4: Other design families
  16. NowProject pages

Next: Alan's review and the fixes

Then: Milestone 4: Evaluation and documentation

Now

GitHub data was read on 2026-10-20 at 16:49 UTC.

Production: success at 411dbfb (head of main in fmegahed/experta).

Branches

No branch other than main is open.

Open pull requests

No pull request is open.

Open issues

Completed work by plan

Tasks done out of the tasks of the plan, the result of the final review, the merge date and the deployment date. A milestone without plan tasks is only in the roadmap above.
PlanTasksFinal reviewMergedDeployed
Milestone 1: R coreR and design rules 12 of 12 tasks 12 of 12 tasks One fix wave; re-review: all findings addressed
Milestone 2: Browser engine and projectsBrowser engine 12 of 12 tasks 12 of 12 tasks Ready with fixes; one fix wave
Milestone 3A: Translation serviceTranslation and LLMs 12 of 12 tasks 12 of 12 tasks Clean after one fix wave
Changes from the first reviewSpecification and scope 5 of 5 tasks 5 of 5 tasks Ready to merge; 7 minor findings deferred
Milestone 3B: InterfaceInterface and help 11 of 11 tasks 11 of 11 tasks 1 Important finding; one fix wave, re-review clean
Milestone 3C: Exports, import and reportExports and report 11 of 11 tasks 11 of 11 tasks 3 Important findings; one fix wave, re-review clean
Alpha releaseDeployment and operations 9 of 9 tasks, plus 2 added during the build 9 of 9 tasks, plus 2 added during the build One fix wave, re-review clean
Alpha minor fixesInterface and help 8 of 8 tasks 8 of 8 tasks One fix wave (11 items), re-review clean
Report print redesignExports and report 8 of 8 tasks, plus 1 added during the build 8 of 8 tasks, plus 1 added during the build One fix wave (10 items), re-review clean
Alan's review and the fixesSpecification and scope 5 of 5 tasks 5 of 5 tasks One fix wave; re-review: all findings addressed
Project pagesProject records 9 of 9 tasks 9 of 9 tasks Final review: ready with fixes; one fix wave Not deployed

Timeline

15 Oct16 Oct17 Oct18 Oct20 Oct Milestone 1: R coreMilestone 1: R core: done, 2026-10-15 to 2026-10-15 Milestone 2: Browser engine and projectsMilestone 2: Browser engine and projects: done, 2026-10-15 to 2026-10-15 Milestone 3A: Translation serviceMilestone 3A: Translation service: done, 2026-10-15 to 2026-10-16 Changes from the first reviewChanges from the first review: done, 2026-10-16 to 2026-10-16 Milestone 3B: InterfaceMilestone 3B: Interface: done, 2026-10-16 to 2026-10-17 Milestone 3C: Exports, import and reportMilestone 3C: Exports, import and report: done, 2026-10-17 to 2026-10-17 Alpha releaseAlpha release: done, 2026-10-17 to 2026-10-18 Alpha minor fixesAlpha minor fixes: done, 2026-10-18 to 2026-10-19 Report print redesignReport print redesign: done, 2026-10-18 to 2026-10-19 Alan's review and the fixesAlan's review and the fixes: now, 2026-10-19 to 2026-10-20 Phase 4: Other design familiesPhase 4: Other design families: planned, first document 2026-10-19, not startedNot started Project pagesProject pages: now, 2026-10-19 to 2026-10-20 DoneIn progressNot started
Table of the bars
Plans from the first commit to the merge. The bar of a plan in progress reaches 2026-10-20. A planned milestone has a short mark at the date of its first document.
PlanStateFirst commitEnd
Milestone 1: R coredone2026-10-152026-10-15
Milestone 2: Browser engine and projectsdone2026-10-152026-10-15
Milestone 3A: Translation servicedone2026-10-152026-10-16
Changes from the first reviewdone2026-10-162026-10-16
Milestone 3B: Interfacedone2026-10-162026-10-17
Milestone 3C: Exports, import and reportdone2026-10-172026-10-17
Alpha releasedone2026-10-172026-10-18
Alpha minor fixesdone2026-10-182026-10-19
Report print redesigndone2026-10-182026-10-19
Alan's review and the fixesnow2026-10-192026-10-20
Phase 4: Other design familiesplanned2026-10-19Not started
Project pagesnow2026-10-192026-10-20

Before the public release

Other open items

The open items of Section 17.1 of the specification that are not above.

Needed by: Phase 2

Needed by: Video release with version 1.0

Needed by: When the authors decide

Needed by: Before a Phase 4 plan